150㎡ high-grade simple style 65 days decoration process

My friend just moved into a new home recently and couldn't wait to send me a picture of the new home. Well, remembering the period of time when he was engaged in decoration, a full 65 days of decoration process , my dark circles have boiled like this:

This friend must not be pro ...

Simply working hard to pay attention, friends lived in the new house if they wished, and the decoration process was bumpy, or the general decoration process did not make any mistakes, so it was based on:

Save money, save time and worry

In principle, it can be said that we efficiently decorated his 150-level high-level simple style! Take the picture as proof:

living room

Entrance

bedroom

kitchen

Restroom

How did we renovate the house?

The decoration is simple to say, but in practice, it is true that the white hair can grow a few, but fortunately, I am an old driver in the decoration industry, so as not to take the detour. Come and see together, how did we spend this inhuman 65 days!

Decoration Day 1

Foreman, designer, owner, on-site accountability, positioning of demolition projects.

Check whether the original wall is leaking, whether the air-conditioning station is complete and easy to install, whether the air-exhaust bathroom exhaust outlet meets the design requirements, whether to re-open the hole, whether the sewer pipe is unobstructed, whether the doors and windows are intact and open smoothly, and whether the wall Obvious cracks, whether the wall has internal insulation needs to be removed, and whether the old public house wall painting needs to be completely removed and repainted.

If there is no problem with the above, the handover is actually completed. The decoration company should be responsible for such problems in the later period. It is best to have a written receipt and signature by both parties.

The owner went to the property to apply for a construction permit, opened water and electricity, and gave all the contact information of the on-site contact person to the foreman, and the foreman arranged to receive the goods.

It is notified that the balcony is measured on site. Some openings require the construction team to cooperate with the door and window construction, and the relevant cooperation projects need to be clear and clear on site.

Decoration Day 2

The decoration team will dismantle the wall, original facilities and openings, remove the wall skin, clean up the site and clean up the garbage in accordance with the requirements of the demolition plan.

As for which walls can be demolished and which cannot be demolished, different structures have different forms, brick-concrete residences are supported by walls, so as long as the walls with a width of more than 120 mm are basically not removable, frame structure and As long as it is not a concrete wall or a block wall, a shear wall structure house can be demolished from the perspective of structural safety.

Judging what structure your house is in, you can find it in your house book and residential instruction manual, and you must consult with the property. After all, they are more professional than you.

Decoration Day 3

Hydropower positioning and material entry, strong and weak wires, water pipes, flame retardant pipes, air switch brands and specifications, need to check one by one according to the contract list standards.

After the hydropower construction is completed, the bricklayers need to check again before entering the field to prevent the stealing of beams and columns. Strong electricity three wires and one tube (one wire and one tube means you are killed)

The water can go to the top as far as possible not to go to the ground, which is convenient for later maintenance. In general, there are pipes and wires that have been worn at home. As long as you do n’t mention it, the conventional treatment method is that he will borrow the previous pipe, but still calculate the money according to the new work. The previous wire will be sold to you, or I ’ll use it for you, but the money is the same, so if you want to be more truthful, that is, after the completion of the water and electricity, and before the bricklayer is done, call the construction unit, designer, field measurement.

Decoration Day 4-5

Inform the floor heating factory to enter the construction site and test the pressure of the water supply pipe. Generally speaking, the initial pressure is 6 kg. Before the boiler is installed, it is normal to reduce the pressure to less than zero kg. If the pressure drop is zero, it must be a leak or damage during construction.

Decoration Day 6-15

Water and electricity materials enter the field and construction, do water pressure test, and waterproof materials enter the field.

Test the pressure of the water supply pipe, the pressure is 8 kg, and the pressure will not drop for half an hour. Spot check several joints. Wrap the napkins at the joints to see if the napkins are wet.

Inform the central air conditioner that the fresh air factory enters the site for simultaneous construction, check whether the air-conditioning pipe insulation cotton package is in place, and the joints and joints need to focus on the insulation package.

Decoration Day 16-19

Waterproof construction, closed water test. 24-hour water shut-off test. There is no water leakage or leakage at the corners of the walls below the floor slab, around the pipes. Must be present in person, preferably with the owner downstairs for acceptance.

Notify the delivery of floor tiles, and agree with the foreman to let the foreman receive the goods, and seal the balcony factory into the construction site.

Check the smoothness of the opening, the integrity of the sealant, shake it vigorously to check the firmness, observe the tightness of the opening fan after closing, and check whether there is water leakage after raining

Decoration Day 20-30

Paving tiles, paving stones, covering pipes, and floor leveling.

After storing water for 8 hours, whether the water blocking threshold of the shower room is leaking, tap the brick with a small hammer to check the empty drums of the wall and floor tiles. A brick knocks at the four corners and listens to the sound in the middle.

The following places must be changed

1. The floor tiles and empty drums that people often walk around must be changed,

2. Wall tiles with a height of more than one meter should be changed, falling easily hits people

3. More than 4 wall tiles in the same area must be changed

4. The bottom of the bed, the bottom of the table and chairs, etc. must be changed where there are bed legs and table legs.

5. In the future, it is necessary to change the place that needs drilling and hanging things

The wooden door is ordered, and the wooden door is measured on site after the bricklayer enters the site, and production begins. The wooden door has a long production cycle. If you want to control the construction period within 60 days, the wooden door must be placed and measured after the bricklayer enters the site.

After the bricklayer is finished, the cabinet is notified, and the countertop cabinet manufacturer starts production after field measurement. Window sill stone, threshold stone, shower room water-retaining bar, purchase after on-site measurement, provide relevant dimensions after the bricklayer enters the site, materials arrive at the site 3 days before the bricklayer is completed, floor after the bricklayer is completed, the total amount of the on-site measurement and accounting.

Decoration Day 31-36

The guest restaurant balcony ceiling, wall panels, soft and hard package base, the door opening is bright. Check the model of the blockboard brand, if the blockboard is to be environmentally friendly, it is best to use E0 grade,

The size of the downlight spotlights must be provided before the ceiling. Light steel keels are recommended for the ceiling keel. The wooden keel has a higher water content. The overall stability is worse than the light steel keel. Notify the integrated ceiling manufacturer to install the wallpaper, wallpaper, wall The cloth is measured on the spot, the wardrobe is measured on the spot and produced, and the shower is measured on the spot and produced.

Decoration Day 38-46

Base layer treatment on the top surface of the wall, installation of gypsum lines, batching of putty, painting of latex paint or wallpaper installation, checking of putty brand model, checking of latex paint according to the standard brand model according to the contract, bagged putty and barreled latex paint need to be on site Then open the face to prevent the old materials from loading new barrels.

Inform the installation of the wooden door, install the door after the putty is completed twice, and the door needs finished product protection.

Check whether the door suction installation is loose, whether it is smooth to open and close, shake it back and forth after closing the door to see if there is a gap, check whether the door cover is loose, and whether the door cover and the door are damaged by paint falling during the installation process. Whether the door lock is loose

Decoration Day 47-49

Inform the cabinets and washbasin cabinet manufacturers to install it 3 days in advance, check whether the appearance is bumped, whether the door opens smoothly, especially the hardware needs to check whether the use is smooth, whether the gap between all of them and the door is even up and down, and the damped hardware damping If it is in place, notify the kitchen appliance 3 days in advance and install the sink on the spot.

The sink is filled with the entire basin of water. After discharging, see if it is smooth, whether the lower drain pipe is leaking, and the connection between the drain pipe and the drain pipe needs to be sealed with glue.

Day 50 of decoration

Install the washbasin, toilet, bathtub, faucet, shower, all materials including angle valves, hoses, etc. to arrive 3 days in advance.

The basin is filled with the whole basin of water. After draining, see if it is smooth, whether the lower drain pipe is leaking, the basin drain pipe needs an independent water trap, and the connection between the drain pipe and the drain pipe needs to be sealed with glue.

Whether the toilet pumping is normal, whether the base is glued, and pump a few more times to see if the base is leaking.

1/4 water is stored in the bathtub.

Decoration Day 51

Floor manufacturers install it one week in advance. Before installation, check whether the ground under the floor is cleaned, and then there will be dust in the future. After installation, check whether the floor is empty, and directly step on one by one.

Decoration Day 52-54

Wardrobe manufacturers install it with one week's notice.

Whether the appearance is bumped, whether the door is opened smoothly, check the edge banding of the board, whether there is any missing or not pasted, especially the laminate inside the cabinet.

Decoration Day 55-60

Installation hardware, lamps, switch panels, mirrors, mirror cabinets, materials arrive 3 days in advance. Shower room manufacturers install it with 3 days notice. Check the waterproof seal around the shower room to see if it opens smoothly. Check the glass 3C logo and factory code, the logo needs to be burned, not posted

Acceptance and repair, review the above check points again

60th day of decoration

In addition to formaldehyde

Let me talk about a big premise first. Formaldehyde after decoration is a continuous release process, so removing formaldehyde is also a continuous process.

Formaldehyde concentration

Formaldehyde is everywhere. Whatever formaldehyde is is nonsense. The indoor concentration is lower than the national standard 0.08mg / m3, which is safe. After an hour of boredom in the room, it is about 1 meter away from the ground near the wall, avoiding the air duct and Measurement results of vents.

The most cost-effective method of removing formaldehyde

· Window ventilation + temperature increase

Most molecules have increased temperature and increased activity, so the best decoration time is to start in March and complete in June. Continue to maintain ventilation for 3 months under the high temperature of summer. The formaldehyde concentration in your home can basically be maintained. It is within the national standard. (Except for the furniture in your house that has a particularly strong taste)

If it is winter, if you have floor heating, you can turn on the floor heating to accelerate the release of formaldehyde

· Fresh air removal of formaldehyde

Formaldehyde is being released all the time. To a certain concentration will be harmful to the health. Fresh air is changed at least every hour of the whole house air, so as long as there is fresh air, the concentration of formaldehyde in your home has been diluted, it is difficult to exceed the standard. (Except for the furniture in your house that has a particularly strong taste)

Of course, you can't live in the first month.

· Air purifier removes formaldehyde

The air purifier is used in conjunction with formaldehyde removal and door and window ventilation. It is not reliable to rely on him to remove formaldehyde. Open the window during the day and open the purifier at night. The main principle of the air purifier is the filter screen and fan. There are now industrial purification plants on the market. The device is very cheap, and the power is very large. Apart from being ugly, there is nothing wrong with it. It is suitable for use in a newly renovated house.

· Photocatalyst to remove formaldehyde

I have learned from colleagues in the industry that the real photocatalyst is an effective way to decompose formaldehyde, but the cost is extremely high, specifically 10,000 words, what you are exposed to are castrated, effective and effective, but also more effective than advertised Far from it, it also needs to be used in conjunction with ventilation.

· Grapefruit peel, activated carbon

Knowing the above principles, you know that this stuff is basically a placebo, and it is slightly useful. The main idea is to comfort yourself. After all, the cost is not expensive.

· Diatom mud

It is still environmentally friendly, but it is not much different from activated carbon by absorbing formaldehyde. It can absorb a little.

I was tired when I went through the decoration process , and I was tired again when I shared the experience of the decoration process today. The key point is: decoration is not tiring.

What, the decoration still uses his own money? ! The Qi family is decorated in installments, with an ultra-low annual interest rate of 3.55% and a maximum loan of 1 million. Apply now to enjoy the discount

The main raw material of SPC Flooring is PVC, PVC is an environmentally friendly non-toxic renewable resource. It has been used in daily life, such as tableware, medical infusion bags and so on, so there is no need to worry about the environmental protection. The main component of Spc Wood Flooring is natural stone powder, which is tested by the national authoritative department and does not contain any radioactive elements. It is a new type of eco friendly flooring material.

Spc Flooring is recyclable,greatly saving wood usage. This is consistent with the national policy of sustainable development for the benefit of society.

191 01

SPC Wood Flooring

Spc Wood Flooring,Anti-Bacteria Spc Flooring,Laminated Spc Flooring,Wooden Design Spc Flooring

Liaoning Schnell Interior Products Co., Ltd , https://www.schnellflooring.com