Decoration design and construction

Story of the owner: What should I do if the renovation is delayed at the end of the year?

The reporter learned from a decoration supervision agency that the extension of the home improvement project is a very common phenomenon. There are reasons for the owner and the reason for the construction party. Why do you postpone it? How can you move in and out of your new home on time? If you can't build a quality project without delay, you can listen to the owner's story and see the experts' suggestions!

Case number one:

Promises to be completed in 2 months to attract owners and to extend the banner for the owners

Because she wanted to celebrate the New Year in the new house, Ms. Chen immediately proceeded with the renovation and chose a decoration company that promised to complete the entire construction period within two months. But so far it has been three months, furniture still can not enter.

Among them, the construction party has found a bunch of reasons for the owners to sign a deferred slip. For example, if the weather is not good, the wall should be aired for a few more days; for example, the original workers are not good, and they say that they are looking for a better worker, but this There is no time for people to wait a few days. For reasons such as this, the construction period has been delayed for more than a month and the house has not been renovated. Ms. Chen feels she has been pitted but she has no alternative

Case 2:

The quality did not pass the rectification of the missed work contract did not indicate no violation of the contract without compensation

During the renovation process, Mr. Li discovered that the construction party had broken the column and shoddy, and then requested a rectification at the time of acceptance. Therefore, the renovation was not completed in accordance with the contract period. Later, it was discovered that in the home-installed contract, the specific amount of compensation for the delay period was not explained at all, and listening to friends said that in this case, it was possible to obtain compensation for the extension. When the repair company was found seeking compensation, the other party simply ignored it and said that it had been rectified.

Case 3:

The material did not arrive on time to disrupt the scheduling of workers and was postponed

The ordered tiles were not delivered on time, so they had to postpone the time to lay the tiles. However, at the beginning of the delay, they found that there was no way behind. Mr. Liu chose the semi-package repair, the main material is to buy their own. Because the tiles did not arrive on time and were delayed for a few days, the workers were disrupted by the schedule. However, the time arrangement was an excuse for delays.

Case four

The acceptance of the owner’s busy work may not affect the next stage

Mr. He chose a very well-known decoration company, but because of the need for frequent business trips, he often has no way to sign and confirm on site at the time of acceptance. The acceptance time is postponed from time to time several times. This is several times, or it is Mr. Lin himself. The time is not good, or if the time schedule of the workers does not come, the little single apartment is also decorated for half a year.

One of the reasons for the delay in renovation: The main material cannot be entered on time

“Text of Residential Decoration Construction Contract”, Article 7 of the contract for breach of contract in Article 2 of the Construction Contract stipulates that if overdue delivery of the project is caused by Party B’s reasons, Party B (construction party) shall compensate Party A (owner) for each overdue day. )yuan. Article VII of the contract stipulates that items 6, 7 and 8 of the liability for breach of contract respectively stipulate delays in starting or stoppage of work due to Party A (owner) reasons. If failure to carry out inspections of concealed works and completed works as agreed, payment is not made according to the time stipulated in the contract. And so on, Party B (construction party) may extend the completion date of the project and have the right to claim compensation for work stoppages, labor and other losses. For every stoppage and workday, Party A shall pay compensation to Party B.

Although it is a model contract for renovation, there is no standard for specific deferred compensation. Different decoration companies are not the same. There are 30 yuan a day, 50 yuan a day, and 150 yuan a day, and there is a project. For 1% of the total cost of construction, some decoration companies do not even have to extend this compensation at all. Han Wei, deputy secretary-general of the Interior Decoration Association Information Committee, reminds consumers that if they do not want to be delayed and have no way to complain, they must specify the specific breach amount and details in the contract terms and then strictly follow the contract.

Do not just ask for fast

The owner hastened to be quick and he would choose a decoration company that promised a short construction period to construct it. In order to sign a single contract, the bad construction team is still unable to do so, and then in the construction process to find a variety of reasons for the owner to sign a deferred bill. For the owner of the rush hour, don’t try to make a big mistake for a small bargain. Although some decoration companies in the north often play slogans for 30 days and 60 days, it usually takes at least 3 months for a flat-level suite to be normally renovated and 4 for a penthouse. From the beginning of the month, the villa will be around 5 months, and it will also change due to factors such as size, difficulty, seasonal climate and distance. The construction period promised by the construction party is too short to be completed on time.

The main material enters the site on time, and the project funds are on time.

In addition to the various delays caused by the construction party, there are many reasons for delaying the owners. The main reason for the owners delaying the construction period was that the main materials could not be approached on time and the construction funds could not arrive on time. In this case, due to the relatively small number of workers and the relatively compact arrangement, once the delay of 2 days for the main material entry does not follow the original plan, it is often several days or even 10 days after the workers enter the court again.

Due to the delay in the construction period, the decoration company and the owner are not willing to be responsible for it. Therefore, Lin Zhengui suggested that the owners should order building materials as early as possible to ensure that materials enter the site on time.

Do not arbitrarily change the design scheme during construction

After the commencement of construction, the constant change of the design plan is also an important factor for delay. Some of them are proposed by the decoration company for increasing budget, designers or construction teams for various reasons, and some are for the owners themselves who did not confirm clearly beforehand and waited until they felt bad after construction.

“When designing a project for the first time, we must fully communicate with the designer. Once the plan is finalized, it should not be easily changed, especially in the construction phase. Once it is changed, it will not only delay the construction period but also increase the budget.” Relevant person in charge Chen Zengyong said.

In addition, if the construction period has been delayed due to construction reasons or there is no delay in the contract, the owner can make up for the situation, sign a supplementary contract, and add the extended compensation clause.

Entrance Decoration Restaurant Decoration Decoration Decoration Decoration Decoration Interior Decoration Decoration Decoration Company Villa Furniture Villa Door Villa Picture Villa Design Villa Apartment Decoration Single Apartment Decoration

There is a limited number of on-site group buying activities. Register now

Related Reading
"Decoration design is free" is that bait designers are more unqualified

In recent years, the pre-design of the room by the decoration company has been recognized by more and more decorators. This reporter learned that many of the city's decoration companies have played a "free decoration design" brand, in order to attract business, whether free design has become the standard for most of the decoration company can receive orders.

2011-05-25 13:53:15
Year-round renovation test construction quality attention to ensure the completion of single decoration

As the year approaches, many consumers with home improvement needs have plans to use the decoration of the Spring Festival holiday. However, the New Year's decoration has always been a problem for many people. Because of the strong mobility of construction workers, the construction process after the year before is not uniform, and the maintenance of the quality of some building materials in winter and winter is a concern for consumers.

2012-01-13 11:27:08
Anti-overfitting Decorate the design from the grab

Have you ever thought that due to the inferior decoration materials and the unsuitable Wenzhou storefront decoration design decoration process, you may make your beautiful new homes that have been thoughtfully decorated to turn into a terrible gas chamber and become an invisible killer of you and your family's health. The poor decoration materials of one side may cause respiratory and skin system lesions, and may even induce a malignant disease such as leukemia. At present, our country is also taking corresponding measures in this regard and put forward the concept of healthy housing...

2012-03-14 12:11:14
Daqing: Half of the regular home improvement companies closed down in half a year

Mr. Zhang, who was responsible for the renovation of building materials, opened a home improvement company with confidence in early 2009. When the company started, the efficiency was very good. However, business began to deteriorate from the middle of last year. At the beginning of this year, Mr. Zhang’s company reluctantly closed.

2011-08-24 11:25:41
Significant tips for signing and claiming a renovation contract

At present, home-installed contracts all over the world are all uniformly formulated contracts. In this contract, users must pay attention to the following issues: 1. The contract must specify the specific requirements and completion date of the renovation. Some consumers did not pay attention to these two points when signing a contract, which created conditions for some decoration companies to overhaul and delay the construction period. 2, in the contract must specify the specific brand or model of decoration materials used, grade, price, etc. to prevent the decoration company to ...

2012-03-14 12:00:55
There have been 0 comments


submit

Recommended Area Popular Atlas Popular Information Popular Questions and Answers Hot Products
Single Apartment Japanese Style Villa Decoration Design Villa Door Cottage Decoration Villa Single Apartment Decoration Renderings Single Apartment Decoration Villa Decoration Design Small Single Apartment Decoration Design Single Apartment Design Villa Decoration Villa Decoration Villa Design Villa Interior Decoration Style High-end Villa Decoration 45 Sqm 2 Rooms One-room decoration renderings 50 flat one-bedroom decoration 70 flat small apartment decoration design 90 square meters house decoration renderings Encyclopedia Yunfu decorative network Zhaoqing decoration network to suppress the price of glass bricks home improvement building materials brand geothermal floor kitchen floor tiles what color aluminum alloy radiator what kind House Style Feng Shui Hanging Hot Machine Ranking Automatic Screw Mechanism Oxygen Machine What Makes Good Smart Vacuum Cleaner Color Steel Tile Tile Decoration Floor Effect Picture Decoration Ceiling Renderings Decoration Bookshelf Effect Picture Decoration Three Room Two Room Effect Picture Rack Picture Combination TV Cabinet Picture Purple Curtain Effect Picture Purple Sofa Picture Purple Bedroom Decoration Effect Picture Wuhu Decoration Xiamen Decoration Extension Installation Yancheng Decoration Yantai Decoration Yichang Decoration Zhenjiang Decoration Zhuhai Decoration Zibo Decoration Wooden Flooring and Floor Tile Which is a good folding bed What makes a good step Yangyang security door How much hoods Wang security door curtain installation method how to spiral staircase top solid size wardrobe how to toilet blocked how to do acrylic latex paint gold leaf mural tiles Spar price price price of water boiler microwave oven hood Price Price

Aluminum LED Down Light

Aluminum Led Down Light,Down Lights Led,Dimmable Led Downlights,Outside Downlights

Jiangmen hengshenghui Lighting Co., Ltd , https://www.jmsunbright.com